Main Stand Electrical Installation | Cambridge City Football Club

Delivering the complete electrical package for Cambridge City Football Club’s new stadium, hospitality facilities and training environments.

 

AB Electrical was appointed to deliver the full electrical infrastructure for the development, working on site for eight months to take the project through installation, testing and certification to final handover.

From LV distribution and stadium lighting to fire alarms, data and security - a complete electrical package delivered for a major new sporting facility.

Scope Included

A comprehensive six-month electrical package covering the new stadium, main stand, hospitality facilities and training environments, followed by an ongoing maintenance and support partnership with the club.

LV distribution and electrical infrastructure across the new stadium development

Complete LED lighting installation throughout the stadium and associated facilities

Emergency lighting systems installed across the development

Fire alarm systems throughout the stadium and operational areas

Data infrastructure to support the club's new facilities

Security infrastructure integrated throughout the development

Complete electrical testing, commissioning and certification

Final project handover followed by ongoing electrical maintenance and support

Project Gallery

Explore the completed Cambridge City Football Club development, including the new stadium, main stand, hospitality areas, training environments and electrical installations delivered throughout the six-month project.

Planning a major commercial electrical project?

From initial electrical infrastructure through to installation, testing, certification and ongoing maintenance, we have the capability to support complex commercial projects from start to finish.